AGL’s $40 Million Upgrade to Clover Power Station Nears Completion
AGL’s Mount Beauty Clover Power Station is on track to complete its $40 million upgrade as early as the start of next year.
First announced in July 2022, the project aims to modernise the 80-year-old facility with the latest technologies, ensuring another 80 years of operation as part of Victoria’s largest hydro-electric scheme.
Major Works and Local Impact
Over the past three years, more than 300 predominantly local workers have contributed to upgrading the ageing infrastructure. Key works include:
- Replacement of turbines and generators
- Installation of high-voltage equipment
- Upgraded control systems for both units
- New main inlet valves
This investment has delivered significant economic benefits to the Mount Beauty region, with contractors supporting local businesses and services.
Technical Achievements
The challenging Tail Bay civil works within Clover Dam were completed last month. The upgrade will increase water flow through the power station from 120 ML/h to 140 ML/h, boosting the overall capacity of the Kiewa Scheme by 14 MW.
The Kiewa Scheme, which runs between Falls Creek and Mount Beauty, includes Makay Creek, Bogong, Clover and West Kiewa Power Stations. Once complete, the scheme will have a total capacity of over 400 MW.
Looking Ahead
The Clover Power Station, originally commissioned in 1945, has presented unique technical challenges during the upgrade. Completion is expected in early 2026, marking a significant milestone for renewable energy generation in the region.
AGL acknowledges the dedication and safety focus of its contract partners throughout this complex project and looks forward to celebrating its successful completion.